A federal judge threw out the IRS notice that tightened safe harbor for large solar. Whether the ruling stands is not settled, so here's who it affects and why most commercial projects shouldn't change course.
Featuring Caleb Quaid, President, Clean Energy Help. Adapted from the SunSmart Engineering × Clean Energy Help × FlaSEIA panel, Commercial Solar in 2026. Watch the clip: "05 - The Safe-Harbor Court Ruling Explained.mp4".
Update, November 6, 2026: The ruling is Oregon Environmental Council v. IRS, decided June 6, 2026 by the U.S. District Court for the District of Columbia (Judge Colleen Kollar-Kotelly). The July 4, 2026 begin-construction date has since passed, so the 5% question now matters for projects that began construction by that date. We have not confirmed that an appeal was filed. The government's 60-day deadline to appeal ran to August 5, 2026 unless it got an extension, so check the court docket before you rely on a 5% start for a project over 1.5 MW. A project that begins construction after July 4, 2026 must be placed in service by December 31, 2027.
The safe-harbor court ruling in June 2026 got a lot of press, and a lot of contractors are now asking whether it changes anything for their projects. For most of them, the answer is no. Clean Energy Help President Caleb Quaid calls it a developing story that matters mostly for very large projects and a lot less than the headlines suggest for a typical commercial job. Here's the timeline, what actually changed, and how to think about it.
The deadline, the executive order, and the lawsuit
Everything traces back to one deadline. The One Big Beautiful Bill Act (OBBBA), signed July 4, 2025, set a termination date for the solar credits. As Caleb puts it: "The One Big Beautiful Bill put a termination date: you must start your project by July 4th of 2026, or place it in service by December 31st of 2027." Beginning construction by that July 2026 date preserved a multi-year window to finish. Miss it, and the project has to be placed in service, meaning it has received Permission to Operate (PTO) from the utility, by the end of 2027.
A project "begins construction" through what's commonly called safe harbor, and there are two recognized tests. The physical work test requires meaningful physical work of a significant nature to have started. The 5% rule lets you establish your start by incurring at least 5% of the project's total cost, usually by purchasing major equipment, even if no one has broken ground. For most developers the 5% rule is the simpler, more common path.
Then the rules shifted. As Caleb explains: "Shortly after, I think the day after, the president issued an executive order that essentially said we're going to make it harder for projects to safe harbor, and if they're over a megawatt and a half, they must meet the physical work test; they can't safe harbor by the 5% rule." In fact, Executive Order 14315 was signed on July 7, 2025, and Treasury followed with IRS Notice 2025-42 on August 15, 2025. For construction starting on or after September 2, 2025, the notice took the 5% option away from wind and from solar over 1.5 megawatts (MW) AC, and forced them onto the harder physical work test.
For utility-scale and large commercial developers, that's a serious problem. "That makes it very hard for a 70-megawatt solar farm to get off the ground," Caleb notes. Lining up real construction on a project that big, on a compressed timeline, is a much heavier lift than incurring 5% of the cost.
What the court ruled, and why the fight isn't over
The notice was challenged in federal court in Washington, D.C. "A couple weeks ago a judge ruled that wasn't allowed," Caleb says, "so a project over a megawatt and a half could still safe harbor with the 5% rule by July 4th." On June 6, 2026, the court vacated Notice 2025-42 in full. It found the IRS acted arbitrarily and capriciously, because it did not explain why it dropped a method in use since 2013 or address the reliance of developers. That restored the 5% option for projects over 1.5 MW, at least for now.
That "for now" is the part to watch. This isn't settled. "I'm not too excited about it," Caleb cautions, "because the administration is appealing, there's going to be another ruling, so even if you follow this guidance in good faith, you're running into how the courts will ultimately decide."
That's the real risk for anyone leaning on the ruling. You could read the current decision, safe harbor a large project under the 5% rule, act entirely in good faith, and still be exposed if an appeals court reverses it. As of this update, the legal ground under a 5%-based start on a big project is provisional.
Who this affects, and who it doesn't
The ruling only bites on projects of 1.5 MW or larger, and as Caleb points out, "most of those already had a lot moving on them." Large developers usually have construction, procurement, and financing well underway before a deadline like this, so a swing in the safe-harbor rules touches fewer projects than the coverage implies.
The bread-and-butter commercial market, rooftops, canopies, and smaller ground-mounts, mostly sits under 1.5 MW and was never the target. Those projects can use the 5% rule the way they always have. That's why Caleb's read is so measured: "It got a lot of press, but in my opinion it's kind of a nothing burger because it doesn't affect too many projects."
None of that means ignore it. It means know whether it applies to you. If your project is under 1.5 MW, the drama was mostly background noise: the 5% rule stayed available, and what matters now is documenting a start on or before July 4, 2026. If your project is over 1.5 MW and began construction on the 5% rule, treat the ruling as helpful but unsettled, and confirm the live status with qualified tax and legal advisors. The window to begin construction under any method closed on July 4, 2026.
The bottom line
- OBBBA set the clock: begin construction by July 4, 2026 (which preserved a multi-year window to finish, and has now passed) or place the project in service (PTO) by December 31, 2027.
- The executive order led to IRS Notice 2025-42, which pushed wind and solar projects over 1.5 MW AC onto the physical work test and removed the 5% rule for them.
- On June 6, 2026, a federal judge vacated the notice and restored the 5% rule for large projects. Whether that holds up on appeal is not settled.
- This mainly affects large projects over 1.5 MW. Most commercial work is under 1.5 MW and could use the 5% rule as usual.
- Don't build a large project's plan on the ruling alone. Even good-faith reliance carries risk until any appeal is resolved, so confirm current status before you act.
How SunSmart Engineering can help
Safe-harbor decisions sit where tax strategy meets real-world engineering, and the timeline pressure makes getting the design and documentation right more important than ever. SunSmart Engineering provides full-service engineering for solar and storage nationwide, helping you scope, design, and document projects so your begin-construction and placed-in-service paths hold up. For the tax and legal side of safe harbor, pair us with a qualified advisor and confirm where the litigation stands. Visit sunsmartengineering.com or call 866-786-8655.
Educational information only, not tax, legal, or engineering advice. Panel quotes are from the June 2026 webinar. Credit, FEOC and deadline facts were re-checked on November 6, 2026 and continue to change. Confirm current requirements with a qualified professional before acting.